The brief
Our education advisory work has grown out of successful projects with Hamwic Education Trust, and this one saw us act as designers, project managers and contract administrators on the tender and construction of a new teaching block at Upper Shirley High in Southampton.
The brief was to provide an additional circa 1,270m2 net of teaching space within the existing school site.
What we did
The solution was to build on part of the school's hard standing playground, adjacent to the existing teaching buildings, replacing old and tired portacabin buildings that were past their intended lifespan. The new facility provides 8 classrooms, 2 DT classrooms and 2 offices over two floors. Temporary classrooms were hired for the duration of the works until the new block was complete.
Following successful planning in June 2017 and the tender process we ran and managed, construction began in September 2017.
The outcome
After an 11 month programme, the teaching block was handed over to the school and trust in early August 2018, leaving time for the school to move in, get familiar with the building and prepare for the start of the new school year in September.
We have since been appointed to design and project manage the construction of a new sports facility at Upper Shirley High.
Related services
Looking for more case studies?
Our ProjectsLet's talk
Got a project like this one?
Tell us what you're working on and we'll take it from there.